One wall, three jobs
A single dark wall carries the INOPRO logo, a screen and the “Testing room” sign, and hides the rooms where visitors try product.
Install began on 10 July. By the afternoon of 11 July the frames were standing and the first wall panels were up.
On 12 July the counters, plants, lighting and graphics went in, and the backlit logo was switched on. A replacement mirror for the testing area arrived from our partner on that last build day.
The booth was handed over on 13 July 2026, ready for the show's opening day.